Noida Global Airport (NIA) remains on display screen with its constructing milestones, with validation flights to check flight procedures besides submitting of its aerodrome license application anticipated by December 2024. Commercial operations at the airport are scheduled to open by the pause of April 2025.
NIA has delivered out of the ordinary growth in the two years for the reason that graduation of constructing process. The airport is made up our minds to play a necessary role in the development of Indian aviation upon completion.
Construction updates
Passenger terminal taking shape: Work on façades and roof underway, set up of baggage facing system is nearing completion, MEP and ending works well underway
READ: WestJet Cargo expands pet transport service to the UK
Runway complete: Asphalt works on the runway are complete. Works on runway markings, plan lights and airfield ground lighting proceed
Air web site visitors set up watch over: MEP works and ending works are in growth at the ATC Tower, whereas navigational aids adore DVOR has been calibrated, and preparations for Instrument Touchdown Machine (ILS) calibration are underway
Partnerships and Operations
Airlines Onboard: Memorandums of Determining (MoUs) with IndiGo and Akasa Air have been signed, with community planning and operational requirements below discussion. Solid curiosity from varied domestic and global carriers
Concessions Awarded: Key aero concessions, along side into-airplane fueling companies, ground facing, and cargo, have been awarded. Non-aero concessions for retail, dining, lounge, responsibility-free, and hotel have furthermore been signed.
Seamless Passenger Chase: Manufacturing facility acceptance tests for key airport programs are complete, and tools has started arriving on residing. Study-in kiosks, self-service secure drops, and e-gates are being examined.
Operational Readiness: Agreements for the most necessary operational and repairs companies, along side airfield lighting, passenger boarding bridges, lifts and escalators have been signed. NIA will notice for aerodrome license by the pause of calendar 365 days 2024.
NIA continues to work closely with its EPC contractor, Tata Projects Dinky, and all stakeholders to hold a excessive momentum of constructing process. The airport is scheduled to delivery operations by the pause of April 2025, ushering in a brand new abilities of connectivity and financial development for the residing.
Noida Global Airport will mix Indian warmth and hospitality with Swiss abilities and efficiency to form a as much as date, client-pleasant blueprint impressed by India. The first segment of the airport will characteristic one runway and one terminal, with the capacity to address web site visitors of 12 million passengers every 365 days. Upon completion of all four constructing phases, the airport will be in a residing to cater to 70 million passengers per 365 days.